Reinforcement of Natural Gas Pipeline System
Latest Project Updates
Crews working for Utilities Kingston have installed and tested approximately 9.0 kilometers of 300mm steel gas pipeline through the rural area and Clyde Industrial Park. This includes Perth Rd, BurBrooke Rd, Sunnyside Rd, the Conservation Area, the 401 Highway, Binnington Ct, Dalton Ave and Sir John A. MacDonald Blvd.
In the Urbanized area crews have installed and tested 6.0 kilometers of 200mm steel gas pipeline. This would include Sir John A. MacDonald Blvd, Johnson St, Albert St, Union St, University Ave. and King St W.
Work on the City Gate Station in Glenburnie has commenced and restoration will resume in the spring. Utilities Kingston would like to recognize the efforts of the contractors and consultants who assisted in this project.