Latest Project Updates

Publication Offers Ravensview Updates

A special advertising section in the August 15 Kingston Whig-Standard newspaper provided a detailed update on Kingston's upgrade of the Ravensview Water Pollution Control Plant. If you missed this special publication, you can download an electronic copy in PDF format from The Whig's own website.
[Download Document]

Biological Aerated Filters Cells

Biological Aerated Filters Cells

Newly filled biological aerated filter cells (pictured at left) will remove dissolved contaminants and provide high-level treatment at the upgraded Ravensview plant. Once in use, the surface of the water will be rough due to aeration and — though likely not beautifully blue — the water will be almost as clean as shown in this photograph.


A look at the progress from above

A look from above

This aerial photograph of the Ravensview site provides an indication of the progress on the $115 million project. Click the image at right to see the new features.

Hotline: 24-hour project information hotline is available at 613-546-0000 ext. 4322

Read our Questions & Answers for site neighbours.

Industry Magazine Focuses on Ravensview

The Ravensview project was featured in the Spring 2008 edition of Influents, the official publication of the Water Environment Association of Ontario. The article notes that "Ravensview's designers wanted local satisfaction combined with a positive global impact... "
[Download Article]


Project Newsletters

Utilities Kingston is keeping project neighbours and other citizens informed of latest developments in the municipality's largest-ever capital project. You can download the latest project newsletters as a PDF files:

Project Newsletters Downloads
June 2008 EditionDOWNLOAD
January 2008 EditionDOWNLOAD
September 2007 EditionDOWNLOAD
May 2007 EditionDOWNLOAD
January 2007 EditionDOWNLOAD
October 2006 EditionDOWNLOAD

Project Links


Ravensview Home

Return to the Ravensview WPCP Homepage.

Project Schedule

An overview of the work at Ravensview through 2009.

Q&A for Neighbours

Answers to common questions for neighbours.

More Links


Pilot Testing

Biologically Aerated Filter (BAF) technology is tested at the Ravensview plant.

Blasting Bulletins

Blasting and excavation alerts for our Ravensview neighbors.

Stay Up Date


Want to receive the latest Ravensview project newsletters via e-mail? Just let us know.

Important Contacts


For concerns or inquiries related to this project, contact Utilities Kingston's Project Manager Allen Lucas at 613-546-1181 ext. 2250 or by e-mail. In his absence, there will be an alternate contact number provided. If you see any environmental emergency or other concern on the site after hours, please call the Utilities Kingston Staff Pager at 613-530-4495 or the Dispatch Office at 613-546-1181 ext. 2151.