Bypass Log For The City of Kingston

Tables 1 and 2 below show the bypass history since the year 2000 for the pumping stations in the City of Kingston. Tables 3 and 4 show the bypass history since September 2006 for the City's combined sewer system (older infrastructure in which there is no separation of surface water runoff and sewage).

For more-detailed information, please contact Utilities Kingston.

Table 1 provides information on the most recent bypass events, including the volume of each overflow and the percipitation that had fallen at the time of each event.

Most Recent Pumping Stations Bypass Events
Last Updated: 07/21/2010
DateCauseVolume (m3)Precipitation (mm)
July 17Power Outage37211.1
June 28Rain1,04720.9
June 22Heavy rain4,33126.5
January 25Heavy rain + Snow Melt29,52636.0
December 3Rain5,14333.0
12

Table 2 provides a breakdown of the yearly bypass totals. The information from Table 1 is included in the Table 2 data.

Historical Pumping Stations Bypass Totals
Last Updated: 07/21/2010
YearEventsVolume (m3)Precipitation (mm)
2010435,27694.50
2009514,138112.0
2008616,488 (2)56.0 (3)
200753,56898.0
200611 (1)140,616306.6
123
(1) Totals include multiple events on the same day. Total percipitation refers to rainfall accumulated during all bypass events. (2) For some events volumes were unknown (3) 2008 rainfall data unavailable until after mid-June; therefore, total is N/A

Table 3 contains the most recent bypass information for the combined sewer system. Information in Table 3 is included in Table 4 data.

Most Recent Combined Sewer System Bypasses
Last Updated: 08/11/2010
DateCauseVolume (m3)Precipitation (mm)
August 10Heavy Rain2,95811.7
August 5Heavy Rain2399.4
July 28Heavy Rain5,27318.9
July 21Heavy Rain2288.2
July 19Heavy Rain1712.0
July 17Heavy Rain1,22511.1
June 28Rain5,53220.9
June 24Rain202.014.6
June 22Heavy rain1,77226.5
May 13Rain457.9
12345

Table 4 shows yearly bypass totals for the City's combined sewer system.

Historical Totals (Since Sept. 1, 2006)
Last Updated: 08/11/2010
YearEventsVolume (m3)Precipitation (mm)
201016136,650207.7
200924314,278447.0
200841626,588N/A (2)
20073185,431350.0
200613139,381 (1)340.3
(1) For some events in September and October 2006, volumes were unknown. (2) 2008 rainfall data unavailable until after mid-June; therefore, total is N/A

Related Links


Sewer Overflow Home

Return to the Combined Sewer Overflow homepage.

City pledges more work to cut sewage bypasses

View the agreement with the Ministry of the Environment commiting the City to further work to control sewage bypasses.

Did you know


Treating Wastewater is a process of cleaning it to remove solids, chemicals and other undesirable material before it is pumped to Lake Ontario.
Kingston has three wastewater treatment plants:

  • Ravensview (Hwy 2)
  • Cataraqui Bay (Behind Dupont)
  • Cana mini(servicing 30 plus houses north of Hwy 15)

Did you know


Treating Water is a process of taking the raw clean water and finishing it, so that it can be filtered out to your home for use
Kingston has three water treatment plants:

  • Central – King St Water Treatment Plant
  • Point Pleasent(Behind Dupont)
  • Cana mini(servicing 30 plus houses north of Hwy 15)